Completed job: Hellenic Community of Ottawa
HMRS finished hazardous-material remediation and demolition on Prince of Wales Drive — a severely damaged structure, taken from removal through demolition to a cleared site.
- Client
- Hellenic Community of Ottawa
- Location
- Prince of Wales Drive, Ottawa
- Status
- Completed past job
What was completed
HMRS completed remediation and demolition on the Hellenic Community of Ottawa property. The work was on Prince of Wales Drive and involved the safe and efficient removal of a severely damaged structure.
The sequence was hazardous-material removal, demolition, and site restoration, with safety and compliance as the stated priorities. The result was a fully cleared, safe, and compliant site ready for redevelopment.
Alexandros R., PMP, posted a public recommendation of the completed job on LinkedIn in 2025.
From start to finish, their team acted quickly to secure the site and worked directly with our Board to carry out the required process for demolition in a professional and efficient manner. We highly recommend HMRS for all your remediation, abatement, and restoration needs, their expertise and responsiveness made all the difference.
Why this sequence matters
Hazardous-material removal comes before demolition, not alongside it. Section 10 of O. Reg. 278/05 puts the examination on the owner before demolition is tendered, and a structure taken down before asbestos-containing material is removed turns the whole site into contaminated debris rather than a clean demolition.
Working with a Board also means the reporting has to survive being read by people who were not on site. A volunteer board approves spending on the strength of a document, not a site walk, and the questions come weeks later from someone who was not in the room. The same requirement applies to a property manager passing a file to an asset manager, and it is why the documentation is built as the work happens rather than assembled at the end.
Securing the site first is the other part worth naming. A severely damaged structure is a liability from the moment it is damaged, and every day it stands unsecured adds exposure that has nothing to do with the remediation scope. Getting the site closed off, then sequencing removal before demolition, is what turns an open-ended hazard into a project with a defined end state.